Metro Manila Strategic Mass Rail Transit Development Project  

Line 2 - Megatren

 

Package 1 - Depot

Contract involves the construction of a depot to house the rolling stocks and other vital facilities of the system to include the rolling stock maintenance facilities, maintenance of way equipment and operations control center.

 

 
n Contractor

 

Sumitomo Corporation

 

 

n Status

 

The package was completed in October 15, 2002.

 

 

n Photos

 

Realignment of Track No. 8 - Depot  Trenching Works at Pump House - Depot

 

Miscellaneous works at Wheel Lathe Building - Depot  Miscellaneous works at Wheel Lathe Building - Depot

 

 

n For more information

 

Please contact:

ENGR. ERIC V. GUTIERREZ

Assistant Project Manager

Tel. # +63(2)832-0432 or at

Tel. # +63(2)853-0042 local 8311

 

 