Light Rail Transit Authority

▲main page

 

 
Project  Updates  
   
LRT Line 2 East/West Extension Project  

 
Description
  • About a 4.14-km. eastern extension of LRT 2 from Santolan Station to Masinag junction in Antipolo City with two (2) stations (Imelda Avenue and Masinag junction) and about 1.62km west extension along C.M. Recto Ave. until Delpan Street passing in front of Tutuban up to the Divisoria Area.
  • No Right of Way acquisition needed for the east extension.
  • Estimated Project Cost - P13,898 B (without rolling stock)
  • The Line 2 East Extension Project was approved by the NEDA Technical Board in 2002 subject to DOF Clearance on financing mix.
  • FS updated in 2006 and further updated in 2009 with a recommendation for inclusion of a 1.6-km. western extension from Recto to Divisoria.
  • With instruction from NEDA Board in 2009 to implement the project on a PPP scheme, if feasible.
  • In the 2nd Quarter of 2009, Marubeni Corporation, together with Katahira and Engineers International, Tonichi Engineering Consultants, Inc. and Oriental Consultants Co., Ltd., through a grant of Ministry of Economy Trade and Industry of Japan, updated the Feasbility Study covering the east and west extension of the existing Line 2 and such study was completed in February 2010.
  • The updated FS of Marubeni was submitted to LRTA in June 2010.
  • Other financing options such as ODA and domestic financing through a syndicated loan from the DBP and LBP are being explored (Line 1 North Extension Project experience will show that cost will be reduced if undertaken through domestic financing).
  • In July 2010, a JICA-Tokyo Mission met with LRTA for initial discussion on the preparation of a full blown Feasibility Study to be conducted by JICA on a grant basis including environmental and social impact of the project.
  • The signing of the Minutes of Discussion on the Preparatory Study for the proposed LRT Line 2 Extension Project was deferred pending the reconfirmation of this project as a priority investment by the next Administration.

Status as of September 30, 2010:

  • The Minutes of Discussion on the Preparatory Study for the LRT Line 2 Extension Project was already signed by JICA-Tokyo representative, LRTA and DOTC.  It includes the Draft Scope of the Preparatory Study for a full blown Feasibility Study to be conducted by JICA on a grant basis.
 
 
For more information

 

Please contact:

Engr. Rodrigo P. Bulario

Project Manager

Tel. # +63(2)853-5810 or at

Tel. # +63(2)853-0041 local 8331

 

 
   
 

 

▲back to top