|
|
n
BRIEF DESCRIPTION OF THE PROJECT |
|
The
project aims to extend the existing 15km LRT Line 1 System southward by
an additional 11.7km, of which approximately 10.5km will be elevated
and 1.2km will be at-grade. The Extension will start from the
existing line's last station at Baclaran and will traverse the cities
of Parañaque and Las Piñas in Metro Manila and reach the
municipality of Bacoor. The extension will initially include 8
new passenger stations with a provision of 2 additional passenger
stations. A satellite depot for light rail vehicle (LRV) storage
and light maintenance will be located at the southern end of the
proposed line. Intermodal facilities will also be installed at
high-demand stations.
The
project will also involve System Enhancement Works over the concesion
period, which would include fleets upgrade, replacement and capacity
improvements. A total of 64 LRVs will be added in 2020 and 8 LRVs
in 2030.
|
|
n
ESTIMATED PROJECT COST (Constant 2005 Prices) |
|
USD 683 M
(Php 36,199 M)
Conversion Rate: Php 53/USD
|
|
n FUNDING SOURCE/ LOAN AMOUNT:
|
FOREIGN Proposed USD 260 Million loan with World Bank
GOP
FOREX CONVERSION: N/A
|
|
n
STATUS (as of 30 May 2008) |
- Ongoing project appraisal by the World Bank
project preparation team.
- MOA between DPWH and LRTA for the ROW was
signed last June 04, 2007.
- MOA between PRA and LRTA was signed on
September 27, 2007.
- Parcellary Survey of 110 affected properties
completed.
- Negotiation with the private property owners
for the acquisition of the ROW is now in full swing to show
GOP's commitment in the immediate implementation and completion
of the Project.
- Evaluation of Consultant for the conduct of
Social Preparation, Community Relations and other Pre-relocation
Activities on going.
- SARO in the amount of Php 1.5 Billion and NCA
amounting to Php 980,627,198.00 for the ROW was issued last
December 27, 2007.
- Sec. Mendoza created the DOTC Project Review
and Evaluation Team for the LRT Line 2 Cavite Extension Project.
- DOTC endorsed to DBM the issuance of MYOA.
- An Inter-Agency meeting was held on April 21,
2008 at the DBM regarding the issuance of the Multi-Year
Obligational Authority (MYOA). The DBM committed to issue
the MYOA as soon as the NEDA-ICC approval is secured for any
project cost adjustment.
- Ridership projection and project estimates
are being updated by the World Bank. The project with its
amended cost will be submitted to Neda ICC for approval.
| ANNUAL FUNDING REQUIREMENTS: (Php M) |
2007 |
2008 |
2009 |
2010 onwards |
TOTAL |
| Right of Way/ Related preparatory Works |
1,563.50 |
2,042.62 |
|
|
3,606.12 |
| Civil Works/ Equipment |
|
1000.64 |
5,300.00 |
7,479.36 |
13,780.00 |
| TOTAL |
1,563.50 |
3,043.26 |
5,300.00 |
7,479.36 |
17,386.12 |
|
|
n TARGETS |
| Activities |
Target Date |
| Issuance of MYOA |
Immediate |
| Launch of Competitive Tender |
After Issuance of MYOA |
| Contract Award |
- |
| World Bank Loan Approval |
- |
| Contract Effectivity |
- |
| Start of Construction |
- |
Start Of Operation (Phase I)
(Baclaran to Dr. Santos Ave., Parañaque) |
- |
Start Of Operation (Phase II)
(Dr. Santos Ave., to Niyog, Bacoor, Cavite) |
- |
|
n
Photos |
|

|
|
n
For more information |
|
Please
contact:
ENGR.
DANILO S. TOLENTINO
Project
Manager
Tel. #
+63(2)854-0980 or at
Tel. #
+63(2)853-0042 local 8361
Fax # 8540980
|
|
|