Light Rail Transit Authority

▲main page

 

 
Project Updates  
 

 
The LRT Line 1 Modernization Phase II-Project  

Modernization and Upgrading of Existing BN ACEC LRVs

OBJECTIVE:                           

To fully modernize the 32 LRV's of Phase I by replacing the old contactors, refurbish relay panel and miniature circuit breakers, and cleaning the chopper box, and also to modernize the remaining yet to be rehabilitated 31 LRV's that were not covered by the initial phase of the modernization program, procure additional spare parts in order to ensure the lifetime of the rolling stock for another 15 years and guarantee the income stream of LRTA.

 

LOAN AMOUNT:           12,258,789.00 Euro

L/A SIGNING DATE:      May 13, 2004

L/A EFFECTIVITY:           February 2, 2005

L/A EXPIRATION:          February 2, 2008

     

Status (as of May 31, 2008)
Cost (Euro) Project % Remarks Actual Accomplishment
A. Procurement / Supply of Spare Parts
  • 100 pieces Traction Motor Armatures
4,276,500.00 (34.89%) 100 units delivered 34.89%
  • Normalization Parts and Spares
1,850,421.00  15.09% 94.50% delivered 14.267%
B. Full Modernization of 63 LRVs  
  • Additional work not covered in the Rehabilitation I contract (32 LRVs) (Replacement of Contactors; cleaning of chopper box; refurbishment relay panel and miniature circuit breaker)
1,074,394.00  (8.76%) 100 % accomplished 8.76%
  • Systematic and Non-systematic replacement of Equipment components of the remaining yet to be modernized 31 LRVs
4,557,483.00  (37.18%) As of january 24, 2008, Modernization of 31 LRV's were completed. 100%Modernization parts were already delivered. 37.18%

C. Technical Assistance

500,000.00  (4.08%) 100% accomplished 4.08%
  TOTAL  12,258,798.00  (100.00%) 99.17%

    Overall Accomplishment:

    Target: 100%%

    Actual: 99.17%

    Variance: -0.83%
 

 

Disbursement Projection (In Euro)                                                                                                             

Cumulative Disbursement (Actual) as of December 2007 Projection for FY 2008 (Million Euro)
€ 12,020,159.00 1st Qtr.€ 0.239M

 

Note:   The negative slippage was due to the hard to find parts to normalize the down BN LRV's which have been unoperational for more than 5 years.  This is beyond the control of the contractor because the said list of parts is not given in the supplemental contract but to be determined by the end user and to submit to PMO for endorsement to the administrator for approval.

 

However, since the sourcing of the last list of the Normalization parts is open ended time activity.  LRTA decided to just charge the cost of the remaining parts to the corporate funds because the contract period will be ended and this supersedes the March report.

 
For more information

 

Please contact:

ENGR. RODRIGO P. BULARIO

Project Manager

Tel. # +63(2)853-5810 / 832-0432 or at

Tel. # +63(2)853-0041 to 60 locals 8330, 8331

 

 

n n n

 
 

 

▲back to top