Modernization and
Upgrading of Existing BN ACEC LRVs

| OBJECTIVE:
|
|
To fully modernize the
32 LRV's of Phase I by replacing the old contactors, refurbish relay
panel and miniature circuit breakers, and cleaning the chopper box, and
also to modernize the remaining yet to be rehabilitated 31 LRV's that
were not covered by the initial phase of the modernization program,
procure additional spare parts in order to ensure the lifetime of the
rolling stock for another 15 years and guarantee the income stream of LRTA.
LOAN AMOUNT: 12,258,789.00 Euro
L/A SIGNING DATE:
May 13,
2004
L/A
EFFECTIVITY:
February 2, 2005
L/A EXPIRATION:
February
2, 2008
|
| Status
(as of May 31, 2008) |
|
|
Cost (Euro) |
Project
% |
Remarks |
Actual
Accomplishment |
|
A. Procurement /
Supply of Spare Parts |
-
100
pieces Traction Motor Armatures
|
4,276,500.00 |
(34.89%) |
100 units delivered |
34.89% |
-
Normalization Parts
and Spares
|
1,850,421.00 |
15.09% |
94.50%
delivered |
14.267% |
|
B. Full Modernization
of 63 LRVs |
- Additional work not covered in the Rehabilitation I
contract (32 LRVs) (Replacement of Contactors; cleaning of chopper box;
refurbishment relay panel and miniature circuit breaker)
|
1,074,394.00 |
(8.76%) |
100 % accomplished |
8.76% |
- Systematic and Non-systematic replacement of
Equipment components of the remaining yet to be modernized 31 LRVs
|
4,557,483.00 |
(37.18%) |
As of january 24,
2008, Modernization of 31 LRV's were completed. 100%Modernization parts were
already delivered. |
37.18% |
|
C.
Technical Assistance |
500,000.00 |
(4.08%) |
100% accomplished |
4.08% |
|
TOTAL |
12,258,798.00 |
(100.00%) |
|
99.17% |
Overall
Accomplishment:
Target:
100%%
Actual: 99.17%
Variance:
-0.83%
Disbursement
Projection (In Euro)
|
Cumulative
Disbursement (Actual) as of December 2007 |
Projection
for FY 2008 (Million Euro) |
| €
12,020,159.00 |
1st Qtr.€
0.239M |
Note: The negative
slippage was due to the hard to find parts to normalize the down BN
LRV's which have been unoperational for more than 5 years.
This is beyond the control of the contractor because the said list
of parts is not given in the supplemental contract but to be
determined by the end user and to submit to PMO for endorsement to
the administrator for approval.
However, since the sourcing of
the last list of the Normalization parts is open ended time
activity. LRTA decided to just charge the cost of the
remaining parts to the corporate funds because the contract period
will be ended and this supersedes the March report.
|
| |
| For
more information |
|
Please
contact:
ENGR. RODRIGO P.
BULARIO
Project
Manager
Tel.
# +63(2)853-5810 / 832-0432 or at
Tel.
# +63(2)853-0041 to 60 locals 8330, 8331
|
|
|