|
Objective |
|
To fully modernize the 32 LRV's of Phase
I by replacing the old contactors, refurbish relay panel and
miniature circuit breakers, and cleaning the chopper box, and also
to modernize the remaining yet to be rehabilitated 31 LRV's that
were not covered by the initial phase of the modernization program,
procure additional spare parts in order to ensure the lifetime of
the rolling stock for another 15 years and guarantee the income
stream of LRTA.
Loan Amount:
12,258,789.00 Euro
L/A Signing Date:
May 13, 2004
L/A Effectivity:
February
2, 2005
L/A Expiration:
February 2, 2009
|
|
Status (as of June 30,
2009) |
|
|
Cost (Euro) |
Project % |
Remarks |
Actual Accomplishment |
|
A. Procurement / Supply of
Spare Parts |
-
100 pieces Traction Motor Armatures
|
4,276,500.00 |
(34.89%) |
100% accomplished |
34.89% |
-
Normalization Parts and Spares
|
1,850,421.00 |
15.09% |
100% delivered |
15.09% |
|
B. Full Modernization of 63
LRVs |
- Additional work not
covered in the Rehabilitation I contract (32 LRVs)
(Replacement of Contactors; cleaning of chopper box;
refurbishment relay panel and miniature circuit
breaker)
|
1,074,394.00 |
(8.76%) |
100 % accomplished |
8.76% |
- Systematic and
Non-systematic replacement of Equipment components
of the remaining yet to be modernized 31 LRVs
|
4,557,483.00 |
(37.18%) |
100% accomplished |
37.18% |
|
C. Technical Assistance |
500,000.00 |
(4.08%) |
100% accomplished |
4.08% |
|
TOTAL |
12,258,798.00 |
(100.00%) |
|
100.00% |
Overall Accomplishment:
Target: 100%
Actual: 100%
Variance: 0.00%
|
|
Disbursement Projection (In Euro) |
|
Cumulative Disbursement (Actual)
as of December 2008 |
| ?
12,258,798.00 |
|
|
For more information |
|
Please contact
Engr. RODRIGO P.
BULARIO
Project Manager
Tel. # +63(2)853-5810 / 832-0432 or at
Tel. # +63(2)853-0041 to 60 locals 8330,
8331
|
|
|