Light Rail Transit Authority

▲main page

 

 
Project Updates  
   
The LRT Line 1 Modernization Phase II-Project
Modernization and Upgrading of Existing BN ACEC LRVs

   
Objective

To fully modernize the 32 LRV's of Phase I by replacing the old contactors, refurbish relay panel and miniature circuit breakers, and cleaning the chopper box, and also to modernize the remaining yet to be rehabilitated 31 LRV's that were not covered by the initial phase of the modernization program, procure additional spare parts in order to ensure the lifetime of the rolling stock for another 15 years and guarantee the income stream of LRTA.

 

Loan Amount:           12,258,789.00 Euro

L/A Signing Date:      May 13, 2004

L/A Effectivity:           February 2, 2005

L/A Expiration:          February 2, 2009

     

Status (as of June 30, 2009)
 
Cost (Euro) Project % Remarks Actual Accomplishment
A. Procurement / Supply of Spare Parts
  • 100 pieces Traction Motor Armatures
4,276,500.00 (34.89%) 100% accomplished 34.89%
  • Normalization Parts and Spares
1,850,421.00  15.09% 100% delivered 15.09%
B. Full Modernization of 63 LRVs  
  • Additional work not covered in the Rehabilitation I contract (32 LRVs) (Replacement of Contactors; cleaning of chopper box; refurbishment relay panel and miniature circuit breaker)
1,074,394.00  (8.76%) 100 % accomplished 8.76%
  • Systematic and Non-systematic replacement of Equipment components of the remaining yet to be modernized 31 LRVs
4,557,483.00  (37.18%) 100% accomplished 37.18%

C. Technical Assistance

500,000.00  (4.08%) 100% accomplished 4.08%
  TOTAL  12,258,798.00  (100.00%) 100.00%

Overall Accomplishment:

Target: 100%

Actual: 100%

Variance: 0.00%
 

Disbursement Projection (In Euro)
 
Cumulative Disbursement (Actual) as of December 2008
? 12,258,798.00

 

 

For more information

 

Please contact

 

Engr. RODRIGO P. BULARIO

Project Manager

Tel. # +63(2)853-5810 / 832-0432 or at

Tel. # +63(2)853-0041 to 60 locals 8330, 8331

 

 
 

 

▲back to top