Brief
Description of the Project |
|
The Project involves the
construction of a 5.7-km. elevated line seamlessly from
Monumento Station of Line 1 to North Avenue Station of Line
3, with three (3) new stations namely: Balintawak, Roosevelt
and a Common Station in front of SM Annex North EDSA plus
Malvar Station in Caloocan City.
|
|
Project Cost |
|
Php6,322.84 Million - Original project cost
Php1,278.80 Million - Additional project cost
Php7,601.64 Million - Adjusted project cost
(including common station)
|
|
Construction
Packages |
Package A:
Construction of Viaduct and Pedestrian Overpasses
Package
B: Construction of Stations and Stations Modifications
Package C:
Electro-Mechanical Works
- EMS - 1: Signaling
- EMS - 2: Telecommunications
- EMS - 3: Automated Fare
Collection System
- EMS - 4: Trackworks
|
|
Project
Duration |
May 2007
- April 2010 (excluding Defects and Liability Period)
- May 2007 - December 2009
(Loop closed)
- Partial Operation of
Balintawak Station - First Quarter 2010
- Partial Operation of
Roosevelt Station - Second Quarter 2010
- Construction Completion
is Targeted on November 30, 2010
|
|
Performance
Accomplishment |
| |
Actual Accomplishment
(As of February 25,
2010)
|
| Consulting Services
- MetroLink Joint Venture |
72.92% |
Package A1(Construction
of Viaduct & Pedestrian Overpasses - Caloocan to
Balintawak Area)
Awarded to DMFB -
Joint Venture |
96.74% |
Package A2
(Balintawak to
Trinoma Area)
Awarded to DMFB -
Joint Venture |
98.41% |
Package B
(Construction of
Stations and Stations Modifications)
Awarded to DMFB -
Joint Venture |
80.56% |
Package C
(revised)
Awarded to Miescor/ GTC JV |
82.12% |
EMS - 1: (Signaling)
Awarded to Siemens-Beta and DMCI JV |
Preparation of
preliminary Design/ Drawings |
EMS - 2:
(Telecommunications) Awarded to
Alcatel-Lucent Phils. |
82.23% |
EMS - 3: (AFCS)
Awarde to AP Trans SA |
83.94% |
EMS - 4: (Trackworks)
Awarded to Daxi-Frateur de Pourcq JV |
95.94% |
| TOTAL PERCENTAGE OF
THE PROJECT |
83.89% |
|
|
Status of the
Project (as of
February 25, 2010) |
|
1. Total Project Completion %:
83.89 2. Total Fund
Releases:
- Total SARO Received:
P 7,551,287,713.00
- Total NCA Releases:
P 4,636,932,143.61 (as of February 2010)
- Total SARO Obligation:
P 7,551,287,713.00
3. 24 Hour/ 7Day-Schedule
Implemented
4.
The Loop
was "Physically Closed" last
December 31, 2009
-
Common Station at SM Annex
- Approved by the NEDA
ICC-CC and confirmed by the NEDA Board on July 7, 2009
- Construction
Completion is targeted on November. 30, 2010
-
On the Additional Station (Malvar Station)
- Feasibility study
completed
|
|
|
|
|
|
For more
information |
|
Please contact:
Engr. FEDERICO J. CANAR, Jr.
Project Manager Tel. # +63 2 851-7338 Tel. # +63 2
853-0042 local 8888 |