|
Brief Description of the Project |
The Project involves the construction of a 5.71-km. elevated
line seamlessly from Monumento Station of Line 1 to North Avenue
Station of Line 3. The scope of works include:
- Civil and Architectural Works, including the construction of
the three new stations (Balintawak, Roosevelt
and North as well as improvements in Monumento Station,
modification of pedestrian overpasses and the provision and
installation of all the required elevators and escalators
thereat.
- Electromechanical Works (except rolling stock) shall
have parameters which are the same as that of CAPEX II-A
|
|
Estimated Project Cost (in Philippine Pesos) |
| Civil and Architectural Works |
P 3,376.36 |
| Electromechanical Works |
1,905.74 |
| Consultancy Services |
317.40 |
| Contingency |
381.00 |
| Subtotal |
P 5,980.50 |
| Inflation Adjustment |
342.35 |
| TOTAL |
P
6,322.85 |
|
|
Project Duration |
- April 2007 - April 2010
- Defects Liability Period: May2010 to April 2012
|
|
Consultancy Services |
The scope of Consulting Services consists of:
- Feasibility Study (demand forecast, financial and economic
analysis, financing strategies)
- Engineering Services
- Environmental Impact Assessment
- Assistance in Bidding
- Construction Supervision
- Project Management Support and Public Relations
- Legal Services
- Defects Liability Support
|
|
Project Status (as of June 03,
2008) |
- Consultancy Contract signed by and between LRTA and
Metrolink on April 23, 2007
- NTP to consultant (May 21, 2007)
- Mobilization of Consultant (May 28, 2007)
Approval of the Project by joint NEDA-ICC and Cabinet Committe
(August 30, 2007)
- NEDA Board appoved the
Feasibility Report and the source of funding (September 18,
2007)
- Publication of Invitation to bid
on October 1, 2007
- Issuance of Eligibility
Documents from October 8 to 22, 2007
- Pre-eligibility Conference of
the interested bidders on November 6, 2007
- Eligibility submission and
opening on November 21, 22, and 23, 2007
- Re-publication of Invitation to
Bid (Packages A1, A2, & B on November 27, 2007
- Re-publication of Invitation to
Bid (Package C) on December 15, 2007
- Eligibility re-submission and
opening (Packages A1, A2 & B) 0n December 19, 20 and 21, 2007
- Purchase of bidding documents
for Civil Works (Packages A1, A2 & B) of eligible contractors
from January 3 to 14, 2008
- Pre-eligibility Conference was
held for Package C on January 8, 2008
- Eligibility submission and
opening of Package C on January 23, 2008
- Pre-bid Conferences were held
for Packages A1, A2 and B on January 22 and 29, 2008
- Selling of Bid Documents to
Pre-qualified Bidders for Package C on February 5, 2008
- Pre-bid Conference was held for
Package C on February 19, 2008
- Receipt of Technical & Financial
Bids and Opening of Technical Bids for Packages A2 & B on March
25 & 26, 2008, respectively
- Receipt of Technical & Financial
Bids and Opening of Technical Bids for Package A1 on March 31,
2008
- Receipt of Technical Proposals
for Packages A1, A2 & B from SBAC for Technical Evaluation
Evaluation on April 4, 2008
- Technical Evaluation of A1 & A2
were completed on April 14, 2008 and advance copy was provided
to LRTA for review
- Bidding for Package C was
declared as failure; the single bidder did not submit a proposal
on April 1, 2008
- Technical Evaluation for Package
B was submitted on April 17, 2008
- Opening of Financial Proposal
for Packages A1 & B on April 24, 2008
- Re-publication for new
eligibility for Package C on April 25, 2008
- Financial Proposal for Package
A2 was opened on May 2, 2008 and the Evaluation Report was
submitted to LRTA on May 7, 2008
- Pre-eligibility Conference for
Package C (Revised) was held on May 7, 2008
- Eligibility submissions for
Package C (Revised) on May 14, 2008 and was declared a failure
- Second invitation for
eligibility of Package C (Revised) was issued on May 20, 2008
- Issuance of eligibility
documents for Package C (Revised) to prospective bidders was
until May 27, 2008
- Pre-eligibility Conference for
Package C (Revised) - second invitation was held on May 28, 2008
- Approval of LRTA on ABC for the
specialist sub-systems (Signaling, AFCS, Track Works and
Telecommunications) on May 30, 20008
|
|
Contract Amount (Metrolink JV) |
P 317,397,661 (Consultancy Services)
|
|
Consultancy Services
- Work Accomplished (May 1 to 31, 2008) |
- The Financial Proposal for
Package A2 was opened on May 2, 2008 and the evaluation Report
for it was submitted to LRTA on May 7, 2008.
- The Pre-eligibility Conference
for Package C (Revised) was held on May 7, 2008.
- On May 9, 2008 a presentation
was made to LRTA on "Cost Changing Exogenous Factors".
This macro-type report was prepared by the Consultant to
demonstrate that there were in fact compelling macro-economic
factors that would justify the upward adjustment of the ABC for
the specialists sub-systems, following the earlier
second-failure of the bidding for Package C.
- On May 12, 2008, LRTA Board
decided that Contracts could be executed for Packages A1 and B
based on the findings presented in the Technical and Financial
Reports for those packages.
- The issuance of NTP for civil
works is scheduled for early June 2008
- On May 14, 2008, the eligibility
submissions for PAckage C (Revised) were received from two
interested bidders. These were DMCI-First Balfour JV and
A.M. Oreta. On the examination of the documents
discrepancies were found in both submissions. The
eligibility evaluation was suspended and the bidders were
suitably advised. The process was to be continued if
acceptable request for reconsideration are received.
- The submission of eligibility
documents by DMCI-First Balfour and A.M. Oreta on May 14, 2008
was declared a failure as the request for reconsideration by the
bidders was denied.
- Following the failure of the
eligibility process for Package C (Revised), a second invitation
was issued on May 20, 2008 for a new eligibility.
- The eligibility documents were
made available to prospective bidders until May 27, 2008.
- Four (4) prospective bidders
procured the eligibility documents. These were:
- A.M. Oreta
- Genials
- MIESCOR
- Comm Builders
- The Pre-eligibility Conference
for the Package C (Revised) - second invitation, took place on
May 28, 2008.
- Alternate procurement of
specialized sub-systems is being studied. Such sub-systems
are:
- Signaling
- Telecommunications Systems
- AFCS
- Trackworks
The revised ABC for these
specialized sub-systems is under preparation based on the
macro-economic findings referred to above.
- It is noted that the award of
the critical Trackworks sub-system must not be delayed beyond
September 1, 2008.
- LRTA-Board Meeting was convened
on MAy 30, 2008 to approve the ABC for the specialist
sub-systems (Signaling, AFCS, Trackworks and
Telecommunications).
- A presentation was made to the
Board on "Cost Changing Exogenous Factors" similar to the
one presented to LRTA on May 9, 2008. The Board accepted
the concept of the cost changing factors but required the
Consultant to modify the multiplier-factors to reflect the
bidding date (May/June 20080 and not May 2009 (middle of the
contract duration), as shown in the said presentation.
- The approval of GPPB dated May
27, 2008 was received. The alternate procurement for the
specialist sub-systems, as proposed by LRTA/Consultant, was
considered acceptable.
- The subsequent procurement
schedule for the Package C (Revised) - rebidding, is as follows:
June 4, 2008
- Opening of Eligibility Documents
June 10, 2008 -
Issue & availability of Bid Docs for Proposal Preparation
June 16, 2008 -
Pre-Bid Conference
July 16, 2008
- Submission of BIds and Opening of Technical
Proposals
July 16, 2008 -
Bid Evaluation (Start)
July 28, 2008 -
Bid Evaluation (Finish)
August 1, 2008 -
Open Financial Proposal/Notification for Negotiation
August 14, 2008 - Notice of
Award/Contract Signing
August 18, 2008 - Issuance of
Notice to Proceed |
|
Important Issues |
- Subsequent to the failure of the
bidding for Package C, LRTA has requested GPPB for the waiver of
the requirement of PCAB license for the procurement of
specialized sub-systems, signaling, Telecommunications, AFCS and
Track Works. Such request has since been granted by GPPB.
Following the waiver by GPPB for
the requirement of PCAB license for specialized
sub-systems, the alternate procurement procedures are being
studied and the eligibility/bid documents are being suitably
modified.
- A discussion is presently taking
place between LRTA and SM Prime Holdings to Finalize the
agreement for the construction of an additional station in front
of the SM annex, between the Roosevelt and North Avenue Stations
of the Line 1 North Extension Project. Such station would
be constructed at the cost of SM.
A suitable cost/benefit analysis
is presently being financed by SM to establish the benefits that
would accrue for LRTA should such an additional station be
constructed.
In view of the fact that the
proposed additional station would also serve Line 7, it has to
be recognized that any agreement between LRTA and SM pertaining
to the additional station would also have to include the
proponents of the Line 7.
|
|
For more information |
Please contact:
Engr. Federico J. Canar
OIC, Project Manager Tel. # +63(2)851-7338 or at Tel. # +63(2)853-0042 local 8888
|
|
|