The LRT Line 1 North Extension Project  
   
Brief Description of the Project

The Project involves the construction of a 5.7-km. elevated line seamlessly from Monumento Station of Line 1 to North Avenue Station of Line 3, with three (3) new stations namely: Balintawak, Roosevelt and a Common Station in front of SM Annex North EDSA plus Malvar Station in Caloocan City.

 

Project Cost

Php6,322.84 Million - Original project cost

Php1,278.80 Million - Additional project cost

Php7,601.64 Million - Adjusted project cost (including common station)

 

Construction Packages
Package A: Construction of Viaduct and Pedestrian Overpasses
  • Package A1 (km 15.133 to km 17.870)(Caloocan to Balintawak Area)

  • Package A2 (km 17.870 to km 20.614)(Balintawak to Trinoma Area)

Package B: Construction of Stations and Stations Modifications

Package C: Electro-Mechanical Works

  • EMS - 1: Signaling
  • EMS - 2: Telecommunications
  • EMS - 3: Automated Fare Collection System
  • EMS - 4: Trackworks

 

Project Duration
May 2007 - April 2010 (excluding Defects and Liability Period)
  • May 2007 - December 2009 (Loop closed)
  • Partial Operation of Balintawak Station - First Quarter 2010
  • Partial Operation of Roosevelt Station - Second Quarter 2010
  • Construction Completion is Targeted on November 30, 2010
Performance Accomplishment
 
  Actual Accomplishment
(As of February 25, 2010)
Consulting Services - MetroLink Joint Venture 72.92%
Package A1(Construction of Viaduct & Pedestrian Overpasses -
Caloocan to Balintawak Area)

Awarded to DMFB - Joint Venture
96.74%
Package A2 (Balintawak to Trinoma Area)
Awarded to DMFB - Joint Venture
98.41%
Package B (Construction of Stations and Stations Modifications)
Awarded to DMFB - Joint Venture
80.56%
Package C (revised)
Awarded to Miescor/ GTC JV
82.12%
EMS - 1: (Signaling)
Awarded to Siemens-Beta and DMCI JV
Preparation of preliminary Design/ Drawings
EMS - 2: (Telecommunications)
Awarded to Alcatel-Lucent Phils.
82.23%
EMS - 3: (AFCS)
Awarde to AP Trans SA
83.94%
EMS - 4: (Trackworks)
Awarded to Daxi-Frateur de Pourcq JV
95.94%
TOTAL PERCENTAGE OF THE PROJECT 83.89%

 

Status of the Project (as of February 25, 2010)
1. Total Project Completion %: 83.89

2. Total Fund Releases:

  • Total SARO Received:    P 7,551,287,713.00
  • Total NCA Releases:      P 4,636,932,143.61 (as of February 2010)
  • Total SARO Obligation:   P 7,551,287,713.00

3. 24 Hour/ 7Day-Schedule Implemented

4. The Loop was "Physically Closed" last December 31, 2009

  • Common Station at SM Annex
    • Approved by the NEDA ICC-CC and confirmed by the NEDA Board on July 7, 2009
    • Construction Completion is targeted on  November. 30, 2010
  • On the Additional Station (Malvar Station)
    • Feasibility study completed

 