Project Updates  
   
The LRT Line 1 North Extension Project  
   
Brief Description of the Project

The Project involves the construction of a 5.7-km. elevated line seamlessly from Monumento Station of Line 1 to North Avenue Station of Line 3, with three (3) new stations namely: Balintawak, Roosevelt and a Common Station.  An additional station (Malvar Station) in Caloocan City shall, likewise, be constructed.

 

Project Cost

  Original Project Cost - P 6,322.84 Million

  Revised Project Cost - P 9,635.06

      (Revised Project Cost includes cost of construction of Common Station, and the proposed Malvar Station and additional one (1) unit rolling stock)

        

           Civil Works ...........................................................5,312.886

           Electromechanical Works ......................................3,835.762

           Consultancy Services.............................................   436.408

           Contingencies........................................................     50.000

           TOTAL PROJECT COST.........................................9,635.056

 

 

Construction Packages
Package A: Construction of Viaduct and Pedestrian Overpasses
  • Package A1 (km 15.133 to km 17.870)(Caloocan to Balintawak Area)

  • Package A2 (km 17.870 to km 20.614)(Balintawak to Trinoma Area)

Package B: Construction of Stations and Stations Modifications

Package C: Electro-Mechanical Works

  • EMS - 1: Signaling
  • EMS - 2: Telecommunications
  • EMS - 3: Automated Fare Collection System
  • EMS - 4: Trackworks

 

Project Duration
May 2007 - April 2010 (excluding Defects and Liability Period)
  • The Loop will be closed by December 2011
  • Commercial Operation of Balintawak Station commenced on March 22, 2010
  • Opening/operation of the Roosevelt Station is targeted by the 4th quarter of 2010
STATUS OF THE PROJECT (as of September 30, 2010)
    Performance Accomplishment
  Actual Accomplishment  (as of September 30, 2010)
Consulting Services - MetroLink Joint Venture 88.22%
Package A1- Viaduct Works Completed (Monumento to Balintawak Area)
(Awarded to DMFB - Joint Venture)
* Combined percentage of completed viaduct works and the on going Overpasses & Walkways works.
*97.85%
Package A2 (Balintawak to Trinoma Area)
(Awarded to DMFB - Joint Venture) *with punchlist items.
**100.00%
Package B (Construction of Stations and Stations Modifications)
Awarded to DMFB - Joint Venture
99.97%
Package C (revised)
Awarded to Miescor/ GTC JV
98.05%
EMS - 1: (Signaling)
Awarded to DMCI-BETA-TEWET JV
60.06%
EMS - 2: (Telecommunications)
Awarded to Alcatel-Lucent Phils.
91.49%
EMS - 3: (AFCS)
Awarde to AP Trans SA
98.57%
EMS - 4: (Trackworks)
Awarded to Daxi-Frateur de Pourcq JV
99.84%
TOTAL PERCENTAGE COMPLETION OF THE PROJECT (excluding common station) 95.59%

FINANCIAL REPORT

  • Total SARO Received:    P 7,551,29M
  • Total NCA Releases:      P 7,158.21M* (as of September 2010) (*Net of Tax Remittance Advice)
  • Total SARO Obligation:   P 7,551,29M

 On Common Station at SM Annex

  • Approved by the NEDA ICC-CC
  • Confirmed by the NEDA Board on July 7, 2009
  • Construction of common station will commence in the 1st quarter of 2011 and will be completed by 1st quarter of 2012

On Additional Station (Malvar Station)

  • The Feasibility Study is completed.

 