Line 1 Modernization Phase II-Project Modernization and Upgrading of Existing BN ACEC LRVs
Objective
To fully modernize the 32 LRV's of Phase
I by replacing the old contactors, refurbish relay panel and
miniature circuit breakers, and cleaning the chopper box, and also
to modernize the remaining yet to be rehabilitated 31 LRV's that
were not covered by the initial phase of the modernization program,
procure additional spare parts in order to ensure the lifetime of
the rolling stock for another 15 years and guarantee the income
stream of LRTA.
Loan Amount:
12,258,789.00 Euro
L/A Signing Date: May 13, 2004
L/A Effectivity: February
2, 2005
L/A Expiration: February 2, 2009
Status (as of June 30,
2009)
Cost (Euro)
Project %
Remarks
Actual Accomplishment
A. Procurement / Supply of
Spare Parts
100 pieces Traction Motor Armatures
4,276,500.00
(34.89%)
100% accomplished
34.89%
Normalization Parts and Spares
1,850,421.00
15.09%
100% delivered
15.09%
B. Full Modernization of 63
LRVs
Additional work not
covered in the Rehabilitation I contract (32 LRVs)
(Replacement of Contactors; cleaning of chopper box;
refurbishment relay panel and miniature circuit
breaker)
1,074,394.00
(8.76%)
100 % accomplished
8.76%
Systematic and
Non-systematic replacement of Equipment components
of the remaining yet to be modernized 31 LRVs
4,557,483.00
(37.18%)
100% accomplished
37.18%
C. Technical Assistance
500,000.00
(4.08%)
100% accomplished
4.08%
TOTAL
12,258,798.00
(100.00%)
100.00%
Overall Accomplishment:
Target: 100%
Actual: 100%
Variance: 0.00%
Disbursement Projection (In Euro)
Cumulative Disbursement (Actual)
as of December 2008