LRT Line 1 Capacity Expansion Project
(Phase II) - Package A and B
Brief Description of the Project
The project involves the acquisition and
installation of air-conditioning units in the old fleet and acquisition
of 12 additional air-conditioned 4-car trains which will require
additional upgrading and equipment for signaling, telecommunications,
traction power supply and distribution, track works, automated fare
collection system and additional civil works for some stations and Depot
to accommodate the new trains and enhance the headway.
The project aims at further expanding the
capacity of LRT Line 1 from 27,000 pphd (Phase I) to 40,000 passengers
per hour per direction (pphd) ( Phase II). Hence, the Phase II
project is intended to cope with the present and expected increase in
the volume of passengers using LRT Line 1 and additional passenger
demand to be generated under the integrated MRT Lines 1, 2, and 3.
All these features are aimed at providing a safe, reliable and
environment-friendly transportation service in Metro Manila.
TOTAL PROJECT COST: (In Millions)
GOP
P 3467.3 M
LOAN/ GRANT PROCEEDS
¥ 22,262.0 M
FUNDING SOURCES:
JBIC's OBUCHI FUNDING (PH-P211)
NG Assistance/ Corporate Funds(OCL)
IMPLEMENTATION SCHEDULE:
(Including Selection of Consultants and inclusive of defect liability
period and Additional Works)
Package A - September 1999 - Jan. 2006 (Original)
- September 1999 - March 2007 (Revised)
- April 2007 - March 2009 (Package A - DLP)
- April 2009 - September 2009 (Extended Consulting Services)
S.A. no.2 - January 8, 2008 - January 28, 2009
Package B - April 2002 - April 2004 (Original)
- April 2004 - July 2004 (Revised)
S.A. no.1A - January 8, 2008 - September 1, 2008
S.A. no.1A & 1B - January 4, 2010 - December 2010
CONTRACTOR AND CONTRACT AMOUNT:
Package A -
SUMITOMO-ITOCHU JOINT VENTURE
Loan Component GOP Counterpart
¥ 15,593,420,106
P 740,695,957.00 (including VAT)
Supplemental Agreement
Workshop Roof and Station Parapets
¥ 415,547,998
P 23,057,282.86
20,803,645.71(VAT)
Package B -
MARUBENI CORPORATION
¥ 2,479,000,000
P 178,706,842.5 (including VAT)
Additional
Works: Off-Shore On-Shore
ACU ¥ 296,268,883 P 17,146,361.75
P 19,231,924.36 ( VAT)
Track Works ¥ 504,171,770 P 74,387,687.81
P 37,962,155 ( VAT)
CONSULTING SERVICES:
Package A & B
Package A -
PACIFIC CONSULTANT INTERNATIONAL, et.al.
¥ 1,643,380,482
P 21,335,497.34 (VAT)
Package B
- ¥ 223,998,075
P 3,164,400.00 (VAT)
Additional Works:
Loan Component
GOP Counterpart
FC
LC
Supplemental Agreement No. 1A
¥ 46,347,000.00 P 3,866,808.51
P 464,017.02 (VAT)
Supplemental Agreement No. 1B
¥ 36,876,582.00 P 6,861,732.96
P 823,407.96 (VAT)
Supplemental Agreement No. 2 ¥ 133,662,287.00 P 54,167,110.00
P 6,089,004.00 (VAT)
TOTAL PROJECT COST:(As of September 30, 2011)
Component
Contract Amount
Payment to Date
Contract Balance
JBIC Fund
LBP-OCL
Consultant
Consulting A
Yen
1,643,380,482.00
1,589,570,972.00
-
53,809,510.00
VAT
21,335,497.34
7,915,525.51
-
13,419,971.83
Consulting B
Yen
223,998,075.00
185,874,151.00
-
38,123,924.00
VAT
3,164,400.00
2,468,309.10
-
696,090.90
Consulting S.A.-1A
Yen
47,187,000.00
6,244,560.00
31,928,400.00
9,014,040.00
Peso
4,037,808.51
-
** 3,315,742.50
722,066.01
VAT
410,400.00
-
-
410,400.00
Consulting S.A.-1B
Yen
36,876,582.00
-
12,486,297.00
24,390,285.00
Peso
** 7,685,140.92
-
** 1,379,625.72
6,305,515.20
Consulting S.A. - 2
Yen
127,855,612.00
31,401,520.00
96,454,092.00
-
Peso
45,541,021.59
-
36,025,600.61
9,515,420.98
VAT
6,089,004.00
-
4,323,072.07
1,765,931.93
Contractor
Package A
Yen
15,593,420,106.00
15,543,725,991.00
-
49,694,115.00
Peso
662,788,215.00
-
575,066,613.25
87,721,601.75
VAT
77,907,742.00
-
67,381,149.80
10,526,592.20
Package A -
Yen
415,547,998.00
415,547,998.00
-
-
Additional Works
Peso
22,537,282.86
-
22,537,282.86
-
VAT
20,803,645.71
2,704,473.94
18,099,171.77
-
Package B -
Yen
800,440,653.00
-
785,627,211.00
14,813,442.00
Additional Works
Peso
81,726,829.96
-
79,143,393.76
2,583,436.20
VAT
9,807,219.59
-
9,497,207.24
310,012.35
** (including VAT)
PHYSICAL STATUS: September 30, 2011
Package A
(LRV's Related System and Civil
Works)
Sub-System
Contract Value %
Progress Percentages (%)
Planned
Actual
A. General
7.61
100
100
B. Rolling Stock
61.71
100
100
C. Signaling System
12.86
100
100
D. Telecommunication
System
3.73
100
100
E. Automated Fare
Collection System
4.34
100
100
F. Power Supply and
Electrical Works
2.86
100
100
G. Track Works
0.88
100
100
H. Overhead Catenary's
System
0.58
100
100
I. Mechanical and
Workshop Equipment
1.36
100
100
J. Operation Control
Center
0.54
100
100
K. Civil Engineering
and Architecture Works
3.53
100
100
PROJECT TOTAL
100.00
100
100
Package B
(Supplemental Agreement No.1A and 1B)
Sub-System
Contract Value %
Progress Percentages (%)
Planned
Actual
A. Track Works
63
100
100
B. Air-conditioning Unit (Adtranz)
37
100
100
PROJECT TOTAL
100
100
100
Note: Financial and Physical Accomplishment of Package B - Extra works
As of September 30, 2011,Track Works - 100% for Foreign Currency and 100% for Local Currency of Milestone Achievement Certificate has been processed and certified by the Engineers and for ACU Works - 95% for Foreign Currency and 83% for Local Currency of Milestone Achievement Certificate.