ITB / RIV No. |
Description |
Date Published |
Closing
Date |
|
L1-NEP |
LRT Line 1 North Extension Project |
11/27/07 |
- |
|
L1-NEP-Package
C |
LRT Line 1 North Extension Project -
Electro-Mechanical Works |
12/17/07 |
- |
|
L1-NEP-Package C (Revised 1.0) |
Design, Manufacture, Supply,
Installation, Testing and Commissioning of Electro-Mechanical Works
|
04/25/08 |
- |
|
05-017-08 |
Contract for Healthcare Services for All
Officers and Employees of LRTA |
05/15/08 |
07/10/08 |
|
L1-NEP-Package C (Revised
2.0) |
Design, Manufacture, Supply,
Installation, Testing and Commissioning of Electro-Mechanical Works
|
05/19/08 |
- |
|
05-040-08 |
Train Number Indicator Power Supply
Module |
05/30/08 |
07/10/08 |
|
05-047-08 |
Cosmolubric HF 122 Series |
05/30/08 |
07/10/08 |
|
05-048-08 |
Mobilube SHC 75W-90 |
05/30/08 |
07/10/08 |
|
signalling |
Signalling Spare Parts |
06/06/08 |
07/10/08 |
|
trackworks |
Trackworks Spare Parts |
06/06/08 |
07/10/08 |
|
L1-NEP -
EMS |
LRT Line 1 North Extension Project -
Electro-Mechanical Subsystems |
06/16/08 |
- |
|
S-001-08 |
Scrap Iron (Rails) |
06/19/08 |
07/10/08 |
|
02-038-08 |
Supply of 500 cubic meters of Track
Ballast (Gravel) |
06/19/08 |
07/27/08 |
|
L1-NEP-Package C (Revised
3.0) Rebid 2 |
Design, Manufacture, Supply,
Installation, Testing and Commissioning of Electro-Mechanical Works
|
06/19/08 |
- |
|
06-022-08 |
Channel Management Module |
06/24/08 |
07/10/08 |
|
06-026-08 |
Primary Fuse |
06/24/08 |
07/10/08 |
|
06-024-08 |
FIAMM 12V. 92Ah/20h to 10.5 at 20
Celsius |
06/26/08 |
07/10/08 |
|
04-051-08R |
Yakal Wooden Sleepers |
06/26/08 |
07/24/08 |
|
06-030-08 |
5/2 Solenoid Valve with Coil 110 VDC |
06/26/08 |
07/26/08 |
|
04-058-08R |
Pandrol Vipa Checkrail Baseplate
Assembly No. 9731 |
06/26/08 |
08/07/08 |
|
06-028-08 |
Various Adtranz Spare Parts |
06/26/08 |
08/07/08 |
|
06-039-08 |
Rubber Element |
06/30/08 |
07/10/08 |
|
07-045-07R |
Resilient Rubber Shunt, Bochumer Verein
or its approved equivalent |
06/30/08 |
07/24/08 |
|
09-058-07 |
Earth Brush Holder |
06/30/08 |
07/24/08 |
|
02-092-07R |
Cylindrical Roller Bearing, Tapered
Roller Bearing |
06/30/08 |
08/07/08 |
|
06-023-08 |
Driving Bevel Gear of Fishbolting Head
14T, Receiving Bevel Gear of Fishbolting Head 14T, |
07/01/08 |
07/24/08 |
|
L1-NEP-EMS-1_Signalling |
LRT Line 1 North Extension Project -
Electro-Mechanical Subsystems: EMS-1: Signalling |
07/02/08 |
- |
|
07-004-08 |
Intermediate Ring |
07/04/08 |
07/24/08 |
|
06-045-08 |
Supply of Labor, Materials, and
Equipment for the Rehabilitation, Replacement of Damaged Floor Tiles
and Application of Anti-Slip Compound at the Platform LRTA Line 2
Stations, Terminals and Link Bridges |
07/04/08 |
08/07/08 |
|
|
|
|
|